Hi,
I would like to release 1.13.3 tarball no later than Tuesday Dec-15. There
is a number of tickets that were not closed and I'm wondering whether to
move them to 1.13.4 or 1.14 Alpha. So far I'm thinking that:
- anything our downstream requires should stay in 1.13.4
- the rest, that's mostly tests and debug message improvements, like
setting the default debug level to 2 should go into 1.14 Alpha.
- #2751 should be deferred until we have the faulty GPO file
- the tickets with patch submitted can stay, we'll see how many
patches we review until the release
Are there other opinions?