Dne 9.12.2014 v 04:06 Adam Williamson napsal(a):
Just to recap, the idea here is that we try to get good coverage on
the
testing as early as possible, with the goal of giving the developers -
especially the anaconda developers - longer to work on the critical
issues. The earlier we identify and report the blocker issues, the
earlier they can get fixed, the better the fixes should be (as they'll
have more time to nail them down well), and the less time we should
spend on emergency last minute test/hack/argue cycles.
This may go along with a possible anaconda plan to freeze development
around Alpha time, in order to reduce the amount of churn and
regressions that occur post-Alpha, which would also make our lives
easier and should hopefully mean that we'd spend a lot of time after
Alpha reporting passes. But I think having the infrastructure for doing
the early testing is useful whether or not that comes to pass.
Hi Adam,
This is very cool! Looking for F22 release exactly according to original
schedule.
Vít