I think there is one thing is missing. How about to schedule marketing and press release too, and their translation?

2009/12/7 Noriko Mizumoto <noriko@redhat.com>
Hi

While checking the schedule, an idea came up in my mind... how big slot do we get for F13 working duration?  Here is the comparison (delays not included). Days are calculated btw start and deadline, so that those may not match with Duration in F12.

[Software]
F12 - 49 days (start 2009-08-04 to 2009-09-22)
F13 - 29 days (starts 2010-02-15 to 2010-03-16)

[Beta Release Notes]
F12 - 34 days (starts 2009-09-08 to 2009-10-12)
F13 - 25 days (starts 2010-03-22 to 2010-04-16)

[GA Release Notes]
F12 - 6 days (starts 2009-11-03 to 2009011-09)
F13 - 6 days (starts 2010-04-20 to 2010-04-26)

[Draft Guides]
F12 - 20 days (starts 2009-09-30 to 2009-10-20)
F13 - 13 days (starts 2010-03-24 to 2010-04-06)

[Final Guides]
F12 - 22 days (starts 2009-10-21 to 2009-11-12)
F13 - 22 days (starts 2010-04-07 to 2010-04-29)

[Websites]
F12 - 19 days (starts 2009-10-28 to 2009-11-16)
F13 - 13 days (starts 2010-04-14 to 2010-05-03)

[o-day release notes]
F12 - 7 days (starts 2009-11-19 to 2009-11-26)
F13 - 7 days (starts 2010-05-06 to 2010-05-13)



cheers



--