Le 1 septembre 2017 11:45:33 UTC-04:00, Jan Kurik <jkurik(a)redhat.com> a écrit :
Hi Translators,
"No More Alphas" Change [1]). What I see as a possibility now is to
have the Software String Freeze milestone one week after Branching and
move Software Translation Deadline to the same date as Beta Freeze.
This gives us the maximum time period between the "Software String
Freeze" and "Translation deadline" we can currently have (even it is
just two weeks).
What do you think ? Will such a timing works for these two milestones
( Software String Freeze & Software Translation Deadline ) ? Or anyone
have a better proposal ?
[1]
https://fedoraproject.org/wiki/Changes/NoMoreAlpha
Thanks for any feedback,
Jan
Hi Jan,
the translation we provides will go to packages and to reach users, it will require a new
package release.
Will packagers be able to do so after beta freeze?
Can we also takes the opportunity to clarify what packages are subject to this schedule? I
understand that at least every project using the Fedora translation platform are asked to
respect this?
Have a nice day, and thank you for your help on this subject!
--
Jean-Baptiste Holcroft