On Wed, 2019-08-14 at 14:26 -0600, Chris Murphy wrote:
Another option here, is applying the last minute blocker to the
Release Target #1 week, and not to the Preferred Target week. Of even,
if it's a 3 day period apply it to the Preferred Target week; and if 7
days apply to Target #1 week.
Hmm, that's an interesting point, I was kinda ignoring the whole
'preferred target' malarkey with this policy. Indeed the go/no-go
meetings are at least initially scheduled in relation to the 'preferred
target' dates.
Still, I don't want to go making the policy more complicated again...
Hmm. Since we've had a proposal for 7 days and a proposal for 3 days,
why not just split the difference and say 5 days? That would be the
Saturday before go/no-go: so anything proposed the week before isn't
covered, but from the weekend on, we're in 'last minute' territory. How
does that sound?
--
Adam Williamson
Fedora QA Community Monkey
IRC: adamw | Twitter: AdamW_Fedora | XMPP: adamw AT happyassassin . net
http://www.happyassassin.net