As we run up to the F26 release, I know we have a number of things still
in flight for the modular release of Boltron. As it is non-blocking to
the release, we won't be holding the release back to make sure Boltron
goes out, which is fine.
However, I notice that the schedule for the F27 Mass Rebuild is July 12
(the day after tomorrow). I am concerned that if Boltron (or anything
else slips), everyone will have to prioritize F27 Mass Rebuild vs F26
final bits & pieces. Would it make sense to consider pushing the Mass
Rebuild out a week to July 19th? Would there be significant downstream
(in schedule terms) effect?
Langdon