Bruno Wolff III <bruno(a)wolff.to> writes:
On Sun, Sep 11, 2011 at 11:13:03 +0200,
MichaĆ Piotrowski <mkkp4x4(a)gmail.com> wrote:
> F16 beta is targeted at 2011-09-27, so there is still a little time to
> upgrade PostgreSQL for this release.
The beta freeze starts two weeks before that and even if it gets in
the next
couple of days it is going to need testing to get positive karma before
making it to updates on time. So there is really extremely little time to
get 9.1 in in time for f16 beta.
Yeah. I have done test packaging of 9.1rc1 already, so it's pretty much
ready to go on my end. I would be prepared to push 9.1 into f16 on
Monday if there were enough people willing to test and up-karma it
before the freeze ... any volunteers out there?
regards, tom lane