Start End Name
Tue 02-Mar Tue 02-Mar Start Splash Screens
Tue 02-Mar Fri 12-Mar Create Splash Screens
Wed 03-Mar Fri 05-Mar Create Alpha Website Banner
Thu 04-Mar Thu 04-Mar Alpha Project Wide Release Readiness Meeting
Tue 09-Mar Tue 09-Mar Alpha Public Availability
Tue 09-Mar Tue 30-Mar Prepare wallpaper for Beta
Fri 12-Mar Mon 22-Mar Finalize Splash Screens
Mon 15-Mar Mon 15-Mar Package: Splash Screens For Rawhide
Please do a careful review of these dates. I had to adjust the overall
schedule for the slip of the Alpha while holding to the originally
scheduled GA date of 2010-05-11. I believe I have reflected everything
correctly. If you see a problem, please let me know.
http://poelstra.fedorapeople.org/schedules/f-13/f-13-design-tasks.html